HOME || ASK A QUESTION/OFFER FEEDBACK || CONTACT US || LINKS || SITE INDEX || STIRLINGLLOYD GROUP

Spray Foam Insulation


Introduction
Frequently Asked   Questions
 Technical Data
 Sheets
AGRISPRAY OS
DURATHERM OS
Bridge Infill Case Study
PIRTHANE ‘‘O’’
Soffit Insulation Case
   Study
TECHNITHERM
Wall Tie Replacement -
   Insulation Case Study
THERMADEK 40 LK
Digester Insulation Case
   Study

Thermadek Winter
   Grade

Winter Application
   Case Study 1
Winter Application
   Case Study 2

THERMADEK Winter Grade

Click here to download/view PDF version


The Client: Major boat builder.
   
The Applicator: Websters Insulation Limited.
   
The Problem: Insulation of a steel-hulled ship, which required a high insulation value and rapid application to achieve a deadline for the client. Only polyurethane foam could achieve the insulation value required at the thickness specified, but the project deadline required that the application be spray applied and be completed when the ambient temperature was below Zero degrees C.
   
The Solution: The steel hull of the ship was sprayed with Thermadek Winter Grade spray foam, at a thickness of 100mm to achieve the required insulation value. Thermadek cured within minutes, even at the sub-zero temperatures and even on such a massive “heat-sink” as the steel hull. Adhesion to the steel was excellent and the cured foam was robust with excellent physical and insulation properties.
   
The Outcome: The client achieved the deadline on the project for his customer who was delighted that the ship was finished on time, despite the adverse weather conditions.


Insulation of a steel-hulled ship: sub-zero temperatures and a massive “heat-sink”.









High insulation value and rapid application. Excellent adhesion. Cured foam robust with excellent physical and insulation properties.